|
DOBOR West Hawaii Projects (November 15, 2011)
Honokohau SBH Phase I Improvements
Scope: Replace loading dock at one boat ramp, water system and electrical improvements Bid Opening: 6/24/2010 (delayed due to bid protest, low bidder Bolton, Inc. disqualified) Contractor: Global Specialties Total Cost: $591,450 Status: Water and Electrical: Issue Notice to Proceed: Nov. 2011 Loading Dock: DOH 401 Water Quality Certification application submitted/pending approval. Once approved, Notice to Proceed for this work will be issued. Onsite Preconstruction Meeting held on 10/26/11 to go over waterline alignment Construction Start: Waterline construction to begin after the Honokohau access road is completed. Please note that the waterline will be installed 5 to 10' away from the road and will not damage the newly constructed roadway.
Honokohau SBH Phase II Improvements
Scope: Access Road, Parking, lighting, and drainage improvements for area adjacent and upgradient of the boat ramps. Consultant: Engineering Partners Status: Ongoing design, $120k approved and an additional $150k requested Funding: Construction funding in FY 2013 Budget ($1,000k Approved and additional $500k requested)
Honokohau SBH Access Road
Scope: Reconstruct approximately 1000 feet of roadway from the Harbor Office to just before the wash down area. Contractor: Willocks Construction Status: Preconstruction meeting scheduled for 10/26/11
Construction Start: November 16, 2011 Construction contact: Bob Bowden, Construction Operations Engineer, ph. 720-963-3595
Honokohau Comfort Station Improvements
South Comfort Station - improvements may include, new toilet partitions, lighting and exterior painting (trim only) North Comfort Station - improvements may include, new epoxy flooring, toilet partition, exterior painting, light fixtures and/or new roofing system Consultant: DOBOR Engineering Funding: Act 164, SLH 2011, Item 9 ($425,000 for Statewide comfort station repairs). Status: The allotment request was approved by the Governor on October 31, 2011
North Kawaihae SBH Improvements
Scope: Repair existing marginal wharf Schedule: First 100' (Mauka) section of the marginal wharf completed in Jan 2011. Remaining 100' (Makai) section of the marginal wharf completed in November 2011. Contractor: Solutions Contracting, Inc. Total cost: $380,047.
North Kawaihae Maintenance Dredging
Scope: Remove sand build-up fronting the boat ramp Bid Opening: 2/24/11 Contractor: George M. Oye, Inc. Contract Amount: $24,980
South Kawaihae SBH Phase I Improvements
Corps of Engineers permit application to install mooring blocks and mooring piles; gangways and marginal wharf within the harbor was submitted and is pending approval. Meeting to be scheduled with DLNR and Corps to discuss permit application status/issues. Contractor: Hawaiian Dredging Construction, Inc. Total Construction Cost: $4,700,000
South Kawaihae SBH Waterline and Roadway Improvements*
Status: Design consultant selected, contract executed Estimated Schedule: Consultant's notice to proceed 10/21/11 Topographic Survey December 2011 Pre-final Design March 2012 Final Design/Permitting Summer 2012 *No construction funds available for this project
Tsunami Damage Repairs
Honokohau SBH Scope: Light post, bull rails & moorings Project Work Sheet (PW) Amount: $12,179 Consultant: Moffatt and Nichol
Kailua-Kona Wharf Scope: Site, boat ramp & comfort station PW Amount: $1,461,210 Consultant: Arnold Okubo and Associates
Keauhou Boat Ramp Scope: Pile, revetment, paving and debris removal PW Amount: $548,690 Consultant: Moffatt and Nichol Status: pending FEMA approval of PWs. Governor released $7.8 million in funding for Tsunami Damage Repairs that was appropriated by the legislature this past session (Act 164, SLH 2011, Item D-7). The Allotment request was approved by the Governor on October 11, 2011.
|